Case Studies: Success Enabler
|
 |
|
Project
Background
Client : A Major E&P Operator
Project : Field development
off of the West African coastline.
Situation : The project
required that upgrades be made to a 5th generation
drilling rig including tree handling and accommodation
prior to going on contract.
Èpeus was asked to identify and
analyse the risk profile of the entire project including
both the operator sponsored upgrades and the drilling
contractor work. Then determine whether the contractors’
project team could achieve its targets and begin transit
to Africa in time to meet the contract start date.
The Findings
The review was conducted at the
beginning of December 2004 and revealed that due to the
risks that the project faced the planned transit start
date of 26th April reflected a 10% probability of target
achievement with a more likely end date being the 3rd of
May 2005 instead.
Project Outcome
The rig left the dock to begin
transit on the 3rd May 2005 reflecting the predicted
outcome from the Success Ènabler study conducted during
the planning phase of the project. Success Ènabler has
been designed specifically to enable you to more
accurately plan projects and take account of previously
unidentified events and impacts increasing your chances
of successful outcome to your project.
|
|
| |
|